Swanton Wind Workshop

The Public Service board provided a workshop on Thursday February 9th starting at 5pm in the Swanton Municipal complex.

Feel free to access the information that was provided prior to the workshop as listed on this page.

click the link above for the full Public Service Board decision on the matter of the workshop and timeline there after.

http://psb.vermont.gov/event/8816-workshop
Docket number 8816
Petition of Swanton win LLC for certificate a public good
Pursuant to title 30 V.S.A § 248

Construction of up to 20 MW wind powered electric generation plant powered by up to seven wind turbines located along Rocky Ridge in Swanton, Vermont.
Procedural order regarding workshop the public service board issued Pre-hearing conference and scheduling order in this proceeding establishing the week of January 2, 2017 at the time for workshop in this matter however due to serious weather the original date was canceled. The town of Swanton filed its recommendation that the workshop be held the evening of February 9th, 2017, at the Swanton Village Complex at 120 First Street in  Swanton. Recommended start time of 5 PM.

Fairfield WILL have visual and possibly audible impacts due to the purposed project. Those who live near the pond are encouraged to attend.
The deadline for filing motions to intervene IS February 16th 21074
The workshop is free to attend. Additional information can be found at the Swanton Wind LLC website as well as the Public Service Board site under docket 8816.

Vermont Public Service Board

http://psb.vermont.gov
Swanton Wind LLC  
https://swantonwindvt.com/permitting-2/
Citizens guide to 248 proceedings is available on Swanton winds site

For additional information please visit:

https://swantonwindvt.org

for information opposing this project

Categories: News

Leave a Reply

Your email address will not be published. Required fields are marked *